Errors to check in an existing draft from the retired Tradie Forms NSW CCEW
Common mistakes when completing a NSW CCEW, and how to avoid them.
Use this page to check records from an existing draft. Complete every new CCEW directly in the BCNSW eCert portal.
Mistake: Missing or incomplete test results, especially insulation resistance, earthing, and RCD tests.
How to avoid:
- Perform all required tests on site before certifying
- Record measured values (e.g. insulation resistance in MΩ) from calibrated equipment
- Use Check All only when every listed test was actually performed
- Complete the Test report section before Certification
See Test report.
Mistake: Wrong or incomplete addresses for customer or installation site.
How to avoid:
- Confirm customer address vs installation site. They are separate fields
- Cross-reference with the job file, contract, or electricity bill
- Complete all required components: street number or lot/RMB, street name, suburb, state, postcode
- For rural properties, verify lot/RMB numbers with council or title documents
See Customer and Installation.
Mistake: Expired or incorrect installer or tester licence numbers and dates.
How to avoid:
- Check licence expiry before signing the certificate
- Verify contractor and qualified supervisor numbers against current NSW records
- Renew stored details after every licence renewal. Do not copy old certificates blindly
See Installer and Tester.
Mistake: Wrong equipment ratings, quantities, or work scope documented.
How to avoid:
- Tick only equipment categories where work was performed
- Record rating and number installed for each selected category
- Use Particulars for model numbers and non-standard configurations
- Align load calculations with installed equipment
See Equipment.
Mistake: Missing meter rows when metering work was done, or incorrect tariff/load figures.
How to avoid:
- When replacing meters, record both removed and installed meters
- Match meter numbers and readings to the physical meters on site
- Confirm estimated load increase reflects new circuits and appliances
See Meters.
Mistake: Finishing a Tradie Forms draft but not submitting the current CCEW in eCert.
How to avoid:
- Enter and check the current details in eCert
- Submit as soon as possible and no later than seven days after completing the tests
- Save the eCert confirmation or reference with the job
See Certification.
Mistake: Wrong electricity distributor or relying on a legacy provider email field.
How to avoid:
- Confirm the distributor against the customer's electricity bill, not postcode alone
- Ausgrid: Sydney, Central Coast, Hunter
- Endeavour Energy: Greater Western Sydney, Blue Mountains, Southern Highlands
- Essential Energy: Regional and rural NSW
- Confirm the required parties and delivery details in eCert
- Check the customer email carefully because eCert uses it to provide their copy
See Installation.
Mistake: Submitting without checking all sections against the job file.
How to avoid:
- Review customer, installation, equipment, meters, installer, tester, test report, and certification in order
- Compare the completed eCert to your site notes before submitting
- Confirm the compliance declaration reflects work you personally verified
- Save the confirmation and check the customer's copy went to the right email