QLD Form 71 Fire Hydrant and Sprinkler Commissioning

Overview and section help for Queensland Form 71 fire hydrant and sprinkler commissioning

QLD Form 71 records commissioning for fire hydrant and sprinkler systems under Queensland Development Code MP 6.1.

Before you start

Have these ready:

  • Site name and address
  • Contractor name
  • Commissioning test type and test date
  • Which systems were tested (hydrant, sprinkler, or combined)
  • Hydrostatic, flow, booster, and sprinkler test readings
  • Equipment and gauge calibration details
  • Compliance outcomes and licensee signature

Check the current requirements for handing the completed form to the building owner or occupier.

Sections in this guide

After export

Keep a copy for your commissioning records and provide the completed PDF to the building owner or occupier as required.