Overview and section help for Queensland Form 71 fire hydrant and sprinkler commissioning

Queensland Government
Record fire hydrant and sprinkler system commissioning under Queensland Development Code MP 6.1 and download the official Form 71 PDF.
Open this formQLD Form 71 records commissioning for fire hydrant and sprinkler systems under Queensland Development Code MP 6.1.
Open Form 71 when the commissioning readings and test-equipment records are ready.
Have these ready:
Check the current requirements for handing the completed form to the building owner or occupier.
Record the job context before you enter test results.
Use saved contractor details if you return to the same sites. Tick sprinkler or combined only when those systems were part of this commissioning visit.
Record the hydrant hydrostatic test against AS2419.1 or AS1851 pressure specifications.
Match the units shown on the form (kPa and L/min). Add comments if the test could not be completed to specification.
Document the test equipment used for hydrant flow and pressure readings.
Part C is not required for orifice testing. If you use more than four devices, note extras in comments or complete another Form 71.
Record hydrant system flow test results under section 10.3 of AS2419.1.
Contact the water service provider if readings do not meet design criteria and there are no on-site faults to explain the result.
Record pump appliance booster test results under sections 10.4 and 10.5 of AS2419.1.
Use the same hydrant location descriptions you would expect the building owner to recognise during a future inspection.
Record the sprinkler hydrostatic test against AS2118.1, AS2118.4, and AS2118.6.
Note any pressure drop or follow-up repairs in the comments so the owner has a clear commissioning record.
Record sprinkler system flow test results for AS2118.1-1999 section 4.14, AS2118.6-2012 section 4, and AS2118.4-2012 section 6.2.
Multiple test points may be required on larger systems. Use comments to list additional points tested if they do not fit the two rows on the form.
Declare compliance outcomes after completing the commissioning tests.
If critical defects were found, check the current notice and reporting requirements for the owner or occupier. Attach repair details to your licensee report when corrective work was done.
Sign off the Form 71 as the appropriately qualified licensee.
Use saved licensee details to prefill repeat fields on your next Form 71. Confirm the declaration text matches your understanding of the test results before download.
Give the completed PDF to the building owner or occupier and keep a copy with the commissioning readings, equipment records, and licensee report. Follow any separate defect notice or corrective-action process that applies.
For worked examples, read the Queensland Form 71 commissioning guide.